1) Gongboxia Hydropower Station
公伯峡水电站
1.
Doing environment protection well during the construction period of Gongboxia Hydropower Station;
做好公伯峡水电站施工期环境保护工作
2.
Review and Summarization the Swirling Spillway Tunnel in Gongboxia Hydropower Station;
公伯峡水电站旋流泄洪洞研究总结
3.
Research and practice about reconstruction of diversion tunnel into permanent rotary internal energy dissipation tunnel: A case study on Gongboxia Hydropower Station;
导流洞改建为旋流式内消能泄洪洞的研究和实践——以公伯峡水电站为例
2) Gongbo Gorge Hydropower Station
公伯峡电站
1.
The foundation excavation and concrete placing of Gongbo Gorge Hydropower Station plant were constructed synchonously.
公伯峡电站厂房基础开挖与厂房砼浇筑平行施工中,在控制爆破方法、爆破规模、一次允许最大起爆药量的同时,对新浇砼面和基础岩石进行了爆破地震波质点振动速度监测,并对不同爆破条件下,新浇砼和基础岩石上的振动衰减规律作了测试。
3) Gongboxia Hydropower Station
黄河公伯峡水电站
1.
Calculation of Design Flood for Gongboxia Hydropower Station;
黄河公伯峡水电站设计洪水计算
2.
In view of optimal design of construction flood for Gongboxia Hydropower Station, this set of method is briefly introduced, and a clearer reply is given to some viewpoints and doubts existed for the time being.
通过黄河公伯峡水电站施工洪水优化设计过程对该套方法作简要论述,并就目前存在的一些观点及疑问给予了较为明确的回答。
4) Gongboxia reservoir
公伯峡水库
1.
The Gongboxia reservoir is situated in Qinghai Province, mainly inundating plains and valleys which are in a good condition for agriculture along both banks of Yellow River.
公伯峡水库位于青海省境内,主要淹没黄河两岸农业条件较优越的川水区,移民搬迁人数虽只有5413人,但淹没损失较大,并对当地经济发展造成了一定程度的影响。
5) Gongboxia Hydro Project
公伯峡水利工程
1.
Application of Construction Technique for Slope Protection of Crushed Concrete Side Wall in Gongboxia Hydro Project of Yellow River;
挤压式混凝土边墙固坡施工法在黄河公伯峡水利工程中的应用
6) Three Gorges Hydropower Station
三峡水电站
1.
Principles and Operation Condition of Reactive Power Regulation of Generating Units at Three Gorges Hydropower Station;
三峡水电站机组无功调节原理及其运行情况分析
2.
Measurement Analysis and Practice of Insulation of Generator Stator Windings on Three Gorges Hydropower Station;
三峡水电站发电机定子绕组绝缘测量分析与实践
3.
Analysis on Vibration Test in Site for Unit of Three Gorges Hydropower Station;
三峡水电站机组现场振动测试分析
补充资料:公伯峡水电站
公伯峡水电站
Gongboxia Hydropower Station
Gongboxia Shuldlonzhan公伯峡水电站(Gongboxia Hydropower Sta-tion)中国近期拟建水电站,位于青海省维化撤拉族自治县和化隆回族自治县交界处,是黄河干流上游龙(羊峡)一青(炯峡)河段的第四个梯级。工程主耍任务是发电并兼顾灌溉、供水。电站装机容黄1500MW,年发电女51.4亿kw·h。电站以330 kV一级电压、4回出线联人西北电力系统。可改善下游16万亩土地徽溉条件。 水文和水库特性坝址控制流域面积143619km.,多年平均流t 717 m3/s,年径流t 226亿m,,经上游龙羊峡水序调节后人库设计和校核洪峰流量分别为五百年一遇5440 m3/s,万年一遇7860 m3/s,年人库沙t 744万t.水库正常蓄水位2005.om,总库容6.2亿m,,调节库容0.75亿m3,为日调节水库.库区淹没耕地7585亩,迁移人口5340人。电站设计水头99.3m,最大工作水头106.6m,最小工作水头%.7 m. 坝址地形地质条件工程区地震基本烈度为姐度,大坝地展设计烈度为8度.坝址位于公伯峡出口段,河道平直,河谷不对称,发育有I、I、,、Iv、v级河流阶地。坝址区主要岩性为片岩、片麻岩及地层上部的花岗岩。自上游右岸至下游左岸展布的岩性软硬相间,接触较X杂。变质花岗岩中断层较发育,主要有F7、F15等。 枢纽布t水电站枢纽由液凝土面板堆石坝、右岸明集引水地面厂房、左岸滋洪道及两岸泄洪建筑物和灌溉取水口组成,见图。 大坝高127m,坝顶长423m,坝顶高租ZOIOm,上、下游坡分别为1:1.4和1,1.5。右岸I级阶地砂砾石层采用棍凝土防诊坡防渗,全长570m。右岸引水集长300m,宽约120m。进水口为混凝土重力式结构,底板高程1975m,最大坝高51.om,5条明钢管直径8.om,地面主厂房尺寸为184.05mX29 mx58.84m,内设5台单机容量3o0MW的水轮发电机组.发电机层高程1907.Zm,水轮机转速为125 r/min,吸出高度为一8.om。左岸开敞式滋洪道,设两个14X16m的表孔,垠顶商程1899m,最大泄量4394 m3/s,挑流消能.放空泄洪洞位于左岸,进口底板高程194Om,岸塔式进水口平板检修门尺寸7 mxgm,出口弧形工作门尺寸7.5 mX6m,全润长642.0m,挑流消能,最大泄t 1190 m3/s。“龙抬头”式右岸深孔泄洪洞,进口底板高程195Om,岸塔式进水口平板检修门8mxll.5m,弧形工作门7mxlom,隧润全长325.6m,最大泄t 2871 m3/s,挑流消能。灌派取水口分设在厂房进水口和滋洪道进水口的右、左侧,取水口中心高程1993.sm,引用流t分别为4.8 m3/s和3 .2 m3/s。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条