2) key process
关键工序
1.
The paper introduced the technological study for PB reactor key process, relating the key process adopted technology and quality control measures, and technological study of important product key process is very important.
本文介绍了PB反应器关键工序的工艺方案研究 ,详细论述了关键工序应采取的工艺技术和过程质量控制措施 ,阐述了重要产品关键工序工艺方案研究的重要
2.
Briefly analyses the quality control on raw material, welding and other key processes, emphasizes the importance of check items detailed.
本文主要介绍了电站锅炉检查重点,对原材料、焊接、无损检验等关键工序的质量问题进行了简要分析,强调了检验项目细化的必要性。
3.
Qualified and fine projects can only be achieved through the following:working out programme of process control;identifying special course and key process ;providing personnel, tools, equipments and materials which can en-sure construction process achieved ssetting up process method; working according to document for control;making various of records.
编制过程控制程序,确定“特殊过程”、关键工序,配备保证过程能力的人员、机具、设备、材料,规定工艺方法,并严格按控制文件执行,作好各种记录,才会筑造出合格、优良的工程。
3) key procedure
关键工序
1.
This article interprets the calculation of 256 m half-through concrete-filled steel tube arch, and the construction process and key procedure.
介绍了青干河大桥设计研究有关情况,并对主跨256m中承式钢管混凝土拱的计算研究作了说明,从设计研究的角度对该工程关键工序及施工方案进行了阐述。
2.
Combined with the seawater desalination project of Hebei Datang Wangtan power plant,it introduces the construction arrangement,main construction plans and debugging plans of the key procedures in electrical system and seawater desalination control system,which is a guidance for the future construction of this field.
通过河北大唐王滩电厂海水淡化工程,介绍了电气系统及海水淡化控制系统关键工序的施工安排、主要的施工方案及调试方案,对于今后同行业的施工具有重要的指导意义。
4) key working procedure
关键工序
1.
Illuminate the three key porcedure of cold drivering steel pipe,to analyses how the defects are happened in the key working procedure of that by the illumination as the base.
阐明了冷拔钢管加工的 3个关键工序 ,在此基础上分析了各关键工序中易产生缺陷的环节及常见缺陷产生的原因 ,对产生的原因进行分析 ,从而对各关键工序进行有效的控制 ,找出相应的消除缺陷的方
2.
It mainly consists of the construction and quality control of the key working procedure-setting up pore canal,reinforcing steel bar passing through,grouting,etc.
结合工程实例介绍了后张法预应力在桥梁施工中的应用,主要包括孔道设置、穿束、张拉、压浆等关键工序的施工和质量控制,以及千斤顶活塞伸长值的理论计算方法,提出确保桥梁结构物满足规范要求的具体措施。
3.
This paper presents a kind of Heuristic Approach, based on key working procedure, to the solving of Job shop scheduling problems.
在分析国内外各种解决生产线作业调度问题方法的基础上,提出了一种基于关键工序排序的启发式调度算法,根据目标函数建立了该算法的数学模型,针对该模型,设计了基于启发式算法的调度程序,仿真算例说明了该算法在求解车间调度问题时的可行性和有效性。
5) Critical operation
关键工序
1.
According to the characteristics of the FJSP,we design a new mutation operator based on critical operations.
本文针对柔性作业车间调度的特点,设计了基于关键工序的变异算子,使变异集中于关键路径,从而提高了变异过程的效率。
6) key construction technology
施工关键工艺
补充资料:施工
施工
construction
shlgong施工(eonstruetion)核电厂建设过程中在工程现场所进行的包括前期工程、土建施工和设备安装在内的全部活动。分施工准备、组织施工和竣工验收三个阶段. 核电厂的建设坚持“安全第一,质量第一”的方针,并依据相关的大纲、程序进行管理。施工准备是保证工程项目具备开工和连续施工的基本条件‘组织施工是工程实施最重要的部分,必须认真做好质量、进度、投资三大控制和安全管理;竣工验收是检查验证完工的建筑物、构筑物及就位的设备、系统的质量、功能符合设计要求,竣工资料真实、完整。核电厂施工要严格按规章制度进行,做到凡事有章可循,凡事有据可查,凡事有人负责,凡事有人监怪。 施工准奋施工准备分为施工组织准备、施工技术准备、施工物资准备及施工现场准备. 施工组织准备工作涉及工程建设的三方,即业主、施工承包单位及监理单位,内容主要包括建立健全组织机构及进行工程管理规划设想.业主的施工管理机构为:施工经理领导下设土建施工、设备安装(核岛、常规岛及电厂辅助设施、电气)、施工支持(文件、测t、设备控制、金属质量、安全)等职能处室,由施工经理统一对外,要求人员精干,职贵明确,建立管理程序,严格按合同和程序办事,高效规范运作。施工单位应按合同规定建立施工组织机构,管理机构要高效精干,建立并实行一级质t保证、两级〔队(厂)与公司级〕质量控制制度,施工机构要与承担的任务相适应.建立、分析人力动员曲线,编写、出版管理程序和工作程序,开展管理及技能培训、工艺评定等。监理单位根据监理委托合同.建立项目监理部,总监理工程师及专业监理工程师应具备核电工程施工管理经验。 施工技术准备主要包括图纸文件及施工组织设计。业主应按合同规定及时将图纸文件交付施工单位,并确认可以使用。施工单位应认真阅读、理解,如有疑问之处,及时向业主提出澄清,由业主或设计单位做出答复。由承包单位编制并经业主(或委托监理单位)审查的施工组织设计是指导现场施工全过程的重要技术文件,其重点是施工方案、进度计划、人员及机具配备、施工平面布置及质量与安全措施.为此,应据此对现场进行统筹规划,科学组织,建立正常合理的施工程序,充分利用空间,争取时间,采用已经成熟的先进施工技术,并进行不利气候因素等风险分析.适当留有余度,以应付施工过程中的某些突发事件。对混凝土人模温度控制、大体积混凝土裂缝控制、反应堆弯顶整体吊装等重要施工方案进行专题分析、论证。 施工物资准备主要包括建筑安装材料、施工机具、永久设备三个方面。对开工必备的材料、机具要安排先期进场。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条