说明:双击或选中下面任意单词,将显示该词的音标、读音、翻译等;选中中文或多个词,将显示翻译。
您的位置:首页 -> 词典 -> 硫酸装置造价估算
1)  Estimating the cost of a sulphuric acid plant
硫酸装置造价估算
2)  cost estimation
造价估算
1.
Application of BP neural network in engineering cost estimation;
BP神经网络在工程造价估算中的应用
2.
Indefinite project cost estimation based on neural network;
基于神经网络非确定性工程的造价估算
3.
With plethora of the historic data,artificial neural network based on BP algorithm provides a practical solution for that problem and it is applied to determine cost estimation through "distilling" rules from the materials of completed projects.
通过案例实证说明,预测值与实际值的相对误差很小,足以满足造价估算的要求。
3)  Cost estimate
造价估算
1.
This paper gives the fuzzy evaluation method of characteristic factors of project,establishes a cost estimate model based on information of real engineering materials and design documents of estimated project.
在工程项目建设的历史资料和设计资料基础上,通过对工程特征因素的模糊评价,充分利用其特征信息,建立了造价估算模型。
4)  sulphuric acid plant
硫酸装置
1.
Increasing mist eliminator capacity in existing sulphuric acid plant installations;
提高现有硫酸装置除雾器的能力
2.
Revamping of pyrite concentrate drying system of Jiangtong-Wengfu's 400 kt/a sulphuric acid plant;
江铜-瓮福400kt/a硫酸装置硫精砂干燥系统改造
3.
Design of fluidized bed roaster of a 100 kt/a sulphuric acid plant;
100kt/a硫酸装置沸腾炉的设计
5)  sulfuric acid plant
硫酸装置
1.
Discussion on some problems existing in the fan of sulfuric acid plant with 800 kt/a capacity and its countermeasures;
800kt/a硫酸装置风机存在问题分析及对策
2.
Retrofits of the Air Purifiers in 6×10~4t/a Sulfuric Acid Plants;
硫酸装置空气净化器的改造
3.
Finally,the congestion problems that hindered the normal sulfuric acid plant production were resolve
本文分析了阳极保护酸冷器堵塞的原因,并采取了相应的改进措施,最终解决了酸冷器堵塞这一阻碍硫酸装置正常生产的难题。
6)  potassium sulphate plant
硫酸钾装置
1.
The experiences in design and construction of a 10 kt/a potassium sulphate plant are described with the emphases on the improvement of insulation,strength and anti-leak of reaction furnace, as well as product propeller based on the experiences of other plants of the same kinds.
介绍10k/a硫酸钾装置的设计和施工经验,重点介绍根据其它同类装置的经验和教训对反应炉的保温、强度、防渗漏及成品推进器所进行的一些改进。
补充资料:发电工程造价


发电工程造价
power project construction cost

fadion gongeheng zoojlo发电工程造价(power projeet constructioncost)指发电工程从前期工作开始,到投产发电的全部工程费用。它因内容不同可分为发电工程静态投资、发电工程动态投资。 发电工程静态投资由建筑工程费、设备购!费、安装工程费、其他费用、基本预备费和材料价差组成,其反映的是某一价格水平年的静态造价水平。1998年价格水平中国内发电工程单位造价水平为:2x300MW国产引进型机组新建4422元/kW,扩建3759元/kw,4台机组时4090元/kw;2X600MW国产引进型嫌煤机组新建3675元/kW,扩建3381元/kw,4台机组时3528元/kw;2 x 300 MW等级进口嫩煤机组新建5010元/kw,扩建4460元/kw,4台机组时4735元/kW;2x600MW等级进口燃煤机组新建4640元/kw,扩建4450元/kW,4台机组时4545元/kW。 发电工程动态投资由发电工程静态投资、价差预备费和建设期贷款利息组成,其中价差预备费是指工程从编制年至竣工年期间建筑工程费、设备购置费、安装工程费、其他费用上涨而预备的费用;建设期贷款利息是指工程项目的各类融资在建设期发生的利息。按电力工程单机竣工结算办法,第一台机组及公用系统所发生利息计算到第一台机组投产前一季度,第二台机组投资所发生的利息计算到第二台机组投产,以下类推。1”8年审批的发电工程初步设计概算动态投资情况如下:2台30万新建国产机组为4997元/kW,2台60万扩建国产机组为4481元/kW,2台35万新建进口机组为5588元/kW,2台“万新建进口机组为6388元/kW。由于价差预备费、建设期贷款利息与国民经济发展情况、物价上涨情况、利息变化情况有关,而这些因素往往具有不可预见性,因此从1995年起对工程概算执行“静态控制,动态管理”的政策,即控制静态投资在批准的额度以内,动态投资则可根据实际情况进行调整。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条