1) dam anti-seepage project
大坝渗控工程
1.
order to insure construction quality of dam anti-seepage project, the supervision engineer need sign and issue permission before every grouting unit started construction, the grouting data were recorded by automatic graphic instruments during whole construction period, quality was examined hole by hole, as well as through taken cores and water pressure tests.
为做好洪家渡水电站大坝渗控工程的施工质量控制,监理工程师在施工前、施工过程中对每个灌浆单元(灌区)均实行签发钻灌开工证制度、帷幕灌浆采用灌浆自动记录仪记录整个灌浆过程的灌浆参数、帷幕灌浆实行单孔验收制度、及时布设质量检查孔进行取心及压水试验等,为确保灌浆施工质量起到了有力的保障作用。
2) seepage control engineering
渗控工程
1.
And rotary orifice lute could overcome difficulties caused by traditional orifice lute,and has successfully been applied in seepage control engineering of Goupitan Hydropower Station.
旋转式封闭器能解决这一系列问题,并已成功地在构皮滩水电站渗控工程中运用。
3) design for seepage control of dam
大坝渗控设计
4) the Daguangba project
大广坝工程
5) seepage control of darn foundation
坝基渗控
6) dam seepage
大坝渗流
1.
Based on Guidelines for Reservoir Dam Safety Evaluation(SL 258—2000),a seepage stability evaluation for the dam of Xiashan Reservoir was carried out by analysis of the monitoring data of dam seepage with finite element method(FEM) and analysis of its operation behavior.
按照SL 258—2000《水库大坝安全评价导则》要求,采用渗流观测资料分析、渗流有限元计算分析及运行表现分析方法,对峡山水库大坝渗流安全进行评价。
2.
Correlation between factors has an effect on the analysis of dam seepage observation data.
大坝渗流观测资料分析中,各因子间常存在不同程度的相关性,这种相关性有时会对分析效果产生较大的影响,另外,通常的回归模型为线性模型,难以精确反映一般为非线性函数的因变量的变化规律。
补充资料:大坝、水库工程特别除外责任条款
大坝、水库工程特别除外责任条款
[大坝、水库工程特别除外责任条款]涉外建筑工程保险中承保大坝、水库建筑工程的除外责任条款。承保大坝、水库工程,必须附加本条款。根据该条款规定,对下列费用或损失均不负赔偿责任:软石地段灌水泥浆或采取的特别安全措施;排水费用;系统的机器损坏;防止地下水的绝缘或其他装置;被保险人未能及时采取相应措施而导致坡度腐蚀的处理费用;滑坡;基础不实引起的地陷、裂口或渗漏。