1.
The facilities for environmental protection of a coal mine construction project must be designed, constructed, checked and accepted, and put into use simultaneously with the main project.
煤矿建设项目的环境保护设施必须与主体工程同时设计、同时施工、同时验收、同时投入使用。
2.
combined heating and power supply installations, or installations for central heating should be designed, constructed and put into operation simultaneously with the constructing projects in question.
热电联供和集中供热设施应当与建筑工程同时设计、同时施工、同时交付使用。
3.
Article 14 Facilities for prevention and control of environmental noise pollution must be designed, built and put into use simultaneously with the main part of a construction project.
第十四条 建设项目的环境噪声污染防治设施必须与主体工程同时设计、同时施工、同时投产使用。
4.
Water and soil conservation facilities in a construction project must be designed, constructed and put into operation simultaneously with the principal part of the project.
建设项目中的水土保持设施,必须与主体工程同时设计、同时施工、同时投产使用。
5.
The facilities for prevention and control of water pollution must be designed, constructed and put to use or into operation simultaneously with the main part of a construction project.
建设项目中防治水污染的设施,必须与主体工程同时设计,同时施工,同时投产使用。
6.
Article 26. Installations for the prevention and control of pollution at a construction project must be designed, built and commissioned together with the principal part of the project.
第二十六条 建设项目中防治污染的设旋,必须与主体工程同时设计、同时施工、同时投产使用。
7.
Installations for the prevention and control of pollution at a construction project must be designed, built and commissioned together with the principal part of the project.
建设项目中防治污染的设旋,必须与主体工程同时设计、同时施工、同时投产使用。
8.
Constructing Practice of Changing Top Equipment and Coating Inner Wall of Blast Furnace At The Same Time
高炉炉顶设备更换与炉内喷涂同时施工的实践
9.
Safety Precautions for Construction at Normal Operating in Hydrogen Manufacturing Unit
保障制氢装置生产施工同时进行的安全措施
10.
The shape of hole wall is varied accoirding to construction process.
孔壁形状因施工工艺不同而不同,通过孔径测试,可以及时发现施工工艺中的问题。
11.
Study on Method of Construction Contract Price Adjustment under Building Materials Price Fluctuate;
建材价格波动时施工合同价格调整方法的研究
12.
Issues be noticed for signing contract by construction enterprises
施工企业签订承包合同时应注意的事项
13.
Vertical construction joints between sections are formed by temporarily placing a steel pipe, having an outside diameter equal to the width of walling, in the trench at the end of each section.
在每个施工段的末端临时插入一根钢管形成施工段之间垂直的施工缝,该钢管外径与墙同厚
14.
Research on Establishing Environmental Supervision System of "Three Simultaneities Environmental Protection Facilities During Construction Period
建立“施工期“三同时”环境保护措施建设”环境监理制度的分析研究
15.
How the Value of the Engineering Contract Price Realize Based on Time Value;
基于时间价值的工程施工合同价格价值实现差异分析
16.
The necessity of simultaneous double layersspreading for bitumen road surface and analysis of construction operation technics;
沥青路面双层同时摊铺的必要性及施工工艺分析
17.
Abstract: he paper introduces the executing plan and techniacl requirement of grouting technique in impurity fill and states quality control in the execution.
文摘:介绍了注浆技术在杂填土中的施工方案及技术要求,同时阐述了施工质量的控制。
18.
Furthermore, the excavation of the foundation pit is deep, and the surrounding condition is complicated.
同时基坑开挖深度大,周边环境复杂,施工难度极大。