说明:双击或选中下面任意单词,将显示该词的音标、读音、翻译等;选中中文或多个词,将显示翻译。
您的位置:首页 -> 句库 -> 安装与调试
1.
Assembly and adjustment of high atmosphere detection laser radar
高空大气探测激光雷达的安装与调试
2.
Eddy Current Transducer Installation and Debugging in Turbine Axis Displacement and Differential Expansion
汽轮机轴向位移、胀差的安装与调试
3.
Installation and debugging of hydraulic system of bar reheating furnace in Shaoguan Iron and Steel Co
韶钢棒材加热炉液压系统的安装与调试
4.
Installation and Commissioning of Super Large Bore Electromagnetic Flowmeter for Urban Water Diversion Project
城市引水工程超大口径电磁流量计安装与调试
5.
Design, Installation and Adjustment about Dunhua Landfill Leachate Treating Plant;
敦化市垃圾填埋场渗滤液处理设备的设计、安装与调试
6.
Issues on the Debugging and Installation of Sulfur Hexafluoride Recovery Set
SF_6气体处理系统调试与安装中的若干问题
7.
Installs the Debugger Interface for stored procedure debugging.
安装调试程序接口以调试存储的过程。
8.
To Involve in the factory construction and start-up, responsible for production and facility equipment installation, layout, commissioning, and qualification.
参与工厂的建设及试车,负责生产设备的安装,规划,调试及评定。
9.
Co-ordinate the vendor assistance required during the construction and commissioning activities.
在安装和调试期间协调和协助供货商。
10.
Research on the Key Technics during Installation and Commission Process of Large Combined Cycle Units;
大型联合循环发电机组安装调试关键技术与应用研究
11.
Analysis on 300MW Circulating Fluidized Bed Boiler Installation in Thermal Power Plant and Troubleshooting Measures
火电厂300MW循环流化床锅炉安装调试与故障处理分析探讨
12.
Installation Process and System Testing on Electric Leakage Fire Alarm System in the High-rise Building
高层建筑漏电火灾报警系统的安装工艺与系统调试
13.
Practice Teaching of NC Machine Commissioning、Installation and Maintenance Curriculum Based On Working-Oriented
数控机床调试、安装与维修技术课程教学改革实践
14.
Coordinate with sub-contractor on the installation of new equipment and debugging.
负责完成新进设备的安装和调试。
15.
Corrugated line machine installation, machine adjustment.
瓦楞纸板生产线设备安装,机器调试。
16.
The debugger is not properly installed on machine '%1'.
没有在计算机“%1”上正确安装调试器。
17.
Has the machinery been put up ready for the broadcast?
广播机器设备安装调试好了没有?
18.
The period for commissioning shall be Six (6) months from the date of issuance of Certificate of Erection.
调试期为安装证书签发后的陆(6)个月。