说明:双击或选中下面任意单词,将显示该词的音标、读音、翻译等;选中中文或多个词,将显示翻译。
您的位置:首页 -> 句库 -> 加权总完工时间
1.
The Parallel Batch Scheduling Problem with Family Jobs and Equal Processing Time to Minimize the Weighted Total Completion Time
加工时间相同的分族分批排序加权总完工时间问题
2.
Single Machine Scheduling Problem with Minimizing Weighted Completion Times with Resource Constrained;
资源有限的加权总完工时间单机排序问题
3.
A Semi-Online Algorithm for Solving the Single Machine Scheduling Problem to Minimize Total Weighted Completion Time with Discounted Factor
折扣加权总完工时间问题的半在线排序算法
4.
An Unbounded Batch Scheduling Problem with Incompatbile Job Families to Minimize the Weighted Total Completion Time
一类无界的不相容工件族分批排序加权总完工时间问题
5.
The problem of minimizing the total weighted completed time on single batch processing machine is studied.
讨论了单机分批排序问题中目标是极小化加权总完工时间的问题。
6.
Dynamic Programming Algorithm on Two Machines Cross Docking Scheduling with Total Weighted Completion Time;
以总加权完工时间为目标的两台机越库排序的动态规划算法
7.
Minimizing total weighted completion time in semiresumable case of single-machine scheduling with an availability constraint
带不可用时间段的部分可续型单机加权完工时间和调度
8.
A Batching Scheduling Algorithm for Maximizing Total Weigted Number of Jobs Completed in Due Date Window;
交货时间区间内加权完工工件个数最大的分批排序算法
9.
I'll finish the job, no matter how long it takes.
不管花多少时间,我总要完成这项工作。
10.
Analysis of Heuristic Algorithm for the Flexible Flow Shop Weighted Completion Time Scheduling Problem;
柔性Flow shop加权完成时间调度问题的启发式算法
11.
Design and Analysis of Predictive Scheduling Algorithms for Minimizing Total Completion Time Problem;
最小化总完工时间预测调度算法的设计与分析
12.
Decrease duration, so the additional work is done over a shorter period of time
缩短工期,使附加的工作在更短时间内完成
13.
Increase task duration, so the additional work is done over a longer period of time
延长任务工期,使附加的工作在更长时间内完成
14.
Minimizing makespan on a batching machine with batch arrivals
极小化最大完工时间的批到达同时加工排序问题
15.
An Optimal Algorithm of Minimizing the Total Completion on Identical Machine Batching Scheduling Problem;
极小化总完工时间同型机分批排序问题的最优算法
16.
With Learning Effect Minimizing the Total Weighted Completed Time on Batch Processing Machines;
带学习效应的极小化全总完工时间的分批排序问题
17.
Resources will work more hours per day, so the task will take less time to complete
资源每天工作小时数增加,任务将花费较少时间完成
18.
{Overtime work cannot be greater than the total work.}Type an overtime work value less than or equal to the total work.
{加班工时不能大于总工时。}请输入小于或等于总工时的加班工时值。