1) stage construction method
正台阶施工法
2) main step construction
正台阶施工
1.
Take-720 central pump house construction of Renlou Coal Mine for example introduces the main step construction,enlarging roof by reverse,bolting and shotcreting temporary support and second times conerete surpport ect.
以任楼煤矿-720中央泵房施工实践为例,介绍了通过正台阶施工、反向挑顶刷大、锚梁喷临时支护、钢筋混凝土二次支护等施工工艺,确保了巷道的安全、顺利施工。
3) bench mining method
台阶法施工
1.
In order to speed up the quick drivage in large span rock roadway,bench mining method should be used in the drivage.
为了加快大断面岩巷快速掘进,采用台阶法施工,上台阶为巷道拱形部分,下台阶为巷道直墙部分,下台阶滞后上台阶约5 m,上下台阶顺序装药,同时起爆。
4) constructed step
台阶施工
5) three bench construction
三台阶施工
6) bench cut method of keeping core soil
正台阶核心土法
补充资料:施工企业技术组织措施计划(见施工企业技术)
施工企业技术组织措施计划(见施工企业技术)
technical and organize measurement plan in construction enterprise
施工企业技术组织措施杯茹”岑,~‘_:_,organize measurement plan in eonstruetionenterPrise)见施工企业技米管理基本制度。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条