Based on PL 19-3Ⅱpipeine project 28 spool piece installation,all types of spool piece are summarized and analyzed,and then valuable chart between spool piece installation time and fabrication tolerance is produced.
本文通过PL19-3Ⅱ期海管项目28套膨胀弯安装的实例,对各个尺寸的膨胀弯进行总结分析,绘制出具有参考价值的膨胀弯安装时间与预制误差对照表。
2) expansion bend
膨胀弯
1.
The factors that may cause pipeline buckling, such as difference in temperature, properties of groundsill, buried depth and expansion bend are discussed.
结合实际工程,探讨了管线屈曲变形的计算方法,分析了温差、地基土特性、管线埋深和膨胀弯设置等因素对管线屈曲变形的影响,并初步探讨了考虑初始缺陷管线的稳定性分析方法和工程对策。
3) expansion bend
膨胀弯头
1.
Design and analyzing of expansion bends in deck piping of ships;
船舶甲板管系膨胀弯头的设计分析
4) loop expansion bend
膨胀弯管
5) compensating line
膨胀伸缩弯头,热膨胀补偿器,膨胀节
6) expansion U-bend
膨胀U形弯管