说明:双击或选中下面任意单词,将显示该词的音标、读音、翻译等;选中中文或多个词,将显示翻译。
您的位置:首页 -> 词典 -> 巴贡水电站工程
1)  Bakun hydropower project
巴贡水电站工程
2)  Bakun hydropower station
巴贡水电站
3)  Bakun hydroelectric project
巴贡水电工程项目
4)  Bakun Project
巴贡工程
5)  hydropower station project
水电站工程
1.
On the basis of introduction of concept as well as methods of measurement of ecological integrity,effect of construction of Shuangxi hydropower station project on regional ecological integrity is expounded in the paper in terms of three aspects: productivity of natural system,state of stability of natural system,and quality of landscape ecosystem.
在介绍生态完整性的概念及其度量方法的基础上,从自然体系生产力、自然体系稳定状况与景观生态体系质量3个方面,阐述了双溪水电站工程建设对区域生态完整性产生的影响。
6)  hydropower project
水电站工程
1.
Application of decision model of fuzzy multi-attribute to some program optimization of a certain hydropower project;
模糊多属性决策模型在某水电站工程方案优选中的应用
2.
Research on Soil and Water Conservation Monitoring of Hydropower Project in Sichuan Province;
四川省水电站工程水土保持监测研究
3.
The work of time-limit control of a hydropower project should be run through the course from start to finish, it is the effective measure for saving investment and improving economic benefit of the project.
水电站工程工期管理贯穿于工程建设的全过程,工期管理是业主节约投资、提高企业经济效益的有效途径。
补充资料:卡里巴水电站
      20世纪60年代非洲最大的水电站。位于非洲赞比亚和津巴布韦两国交界的赞比西河中游卡里巴峡谷内,距索尔希伯里290km。峡谷内河岸边坡约30°~40°,基岩裸露,是良好的水力开发地址。峡谷长26km,电站建于距峡谷出口2km处。控制流域面积663000km2,多年平均流量1420m3/s。电站包括一座混凝土双曲拱坝和右岸第一期地下厂房,安装机组6台,总装机容量60万kW,年发电量35亿kW·h。1955年开工,第一台机组在1960年5月17日投入运行。第二期地下厂房位于左岸,计划装机90万kW,1988年末已有4台15万kW机组投入运行。它为赞比亚的炼铜业提供了廉价的电力。
  
  电站具有以下主要特点:①有一座128m高的混凝土双曲拱坝,坝顶长620m,其长高比接近5,开创了宽河谷中修建高拱坝的先例。②赞比西河水流充沛,最大流量达17000m3/s。在坝体内开设6个用直升闸门控制的9.1m×9.46m的泄水中孔泄洪,总泄洪流量为9500m3/s,利用挑流消能,水流在坝址下游约100m处落入水垫塘,曾形成较深冲刷坑,但工程至今运行良好,具有较大经济效益。③形成的水库面积5120km2,总库容达1840亿m3,可容纳近4倍的赞比西河年径流量,是20世纪60年代初世界最大的水库。蓄水前曾迁移57000名唐加牧民。④在工程的分期施工导流中,采用拱围堰挡水,使坝体得以快速施工,且很经济。左岸拱围堰高18m,长高比达16,厚度仅1.8m。河床拱围堰下部为两排钢板,中间填压浆混凝土,上部为一般混凝土。这种拱围堰是在电站施工中首次采用并获得成功。
  

说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条