1) Natural caving without floor pillar method
无底柱自然崩落法
2) Sublevel caving without sill pillar
无底柱分段崩落法
1.
Although a lot of research on the high-efficient exploitation field of vein gold deposits is carried out in the theoretical research of mining method and production practice of mines, the sublevel caving without sill pillar has been neglected at all times.
虽然在迄今为止的采矿方法理论研究与矿山生产实践中,对岩金矿床高效开采领域进行了许多研究,但一直忽视了无底柱分段崩落法,使这一安全高效采矿方法未能在岩金矿床得到实际应用。
3) sublevel caving
无底柱分段崩落法
1.
Experiments were conducted to investigate the effects of material strength and hole burden on the blast performance of fan-patterned holes in sublevel caving, and to analyze the factors affecting the effective area of blasting.
实验研究了试件强度与抵抗线对无底柱分段崩落法扇形炮孔爆破效果的影响,分析了有效爆破区域出现在孔底部位而不是孔口部位的原因,揭示了扇形炮孔爆破的方向性与顺势破坏效应,据此讨论了炮孔密集系数的合理取值范围以及孔底起爆的适用条件等;应用试验结果改进北氵名河铁矿扇形中深炮孔的装药结构与起爆顺序,试验区大块率从3·0%降低到1·8%·并杜绝了爆破“隔墙”现象的发生
2.
A computer-aided technical management for sublevel caving is established and its structural design, compositions and functions are introduced.
介绍了一种适用于无底柱分段崩落法的计算机辅助技术管理系统的结构设计、系统组成与功能等。
3.
This paper describes the principles of computer stochastic simulation and the computer program used for simulating the process of ore drawing in Sublevel Caving.
本文主要介绍了计算机随机模拟方法的基本原理及模拟无底柱分段崩落法的程序结构,并结合对无底柱分段崩落法矿石回收率影响因素的分析研究介绍了随机模拟方法在放矿研究中的应用情况。
4) non-pillar sublevel caving
无底柱分段崩落法
1.
Improvement of cutting technology for non-pillar sublevel caving;
无底柱分段崩落法切割工艺的改进
2.
The collusions reveal the elementary mechanism of capping rock collapse and the rules of ground subsidence during the caving process by non-pillar sublevel caving.
以武钢程潮铁矿西区开采为工程背景,采用现场钻孔监测与相似材料模型实验相结合的方法,对无底柱分段崩落法开采过程中顶板围岩的变形和崩落规律进行了系统研究。
5) no sill pillar and high-sublevel caving
无底柱高分段崩落法
1.
Application of no sill pillar and high-sublevel caving in weak orebody mining;
无底柱高分段崩落法在松软矿体开采中的应用
6) Sublevel caving method
无底柱分段崩落法
1.
Study on Reasonable Cut-off Grade for Ore Drawing in Sublevel Caving Method;
无底柱分段崩落法合理放矿截止品位的研究
2.
A case study on sublevel caving method shows how the 3D Studio Max and the Photoshop 6.
本文以无底柱分段崩落法为例 ,介绍用 3DStudioMax和Photoshop6 。
3.
According to underground pressure problem and hard extraction of sublevel caving method, primary work done is set forth as follows:Firstly, according to the results of systematical engineering geological survey, Q system which is well applicable to the conditions of high stress field and RMR method are applied to rock engineering classification.
针对无底柱分段崩落法采矿方法地压显现严重、回采困难等问题,主要开展了如下研究工作:首先,根据东西区矿床工程地质环境调查,采用RMR岩体分类方法和高地应力条件下适应性较好的Q系统,对深部围岩进行工程分类。
补充资料:阶段自然崩落采矿法
阶段自然崩落采矿法
spontaneous block caving method
阶归的自然崩落和拉底空间下部巷道的稳定性密切相关,拉底空间顶板附近的矿石的自然崩落主要靠矿石中的需根据过去和当时的实测资料等来确定。拉切帮槽多拉应力超过了矿石的抗拉强度进行的。而再往上面的用中深孔,通常只有在掘进切帮巷道还不能有效削弱矿石的自然崩落则主要是靠矿石中的压应力超过矿石待自然崩落矿体与周围矿岩间的联系时,才拉切帮槽。的抗压强度进行的。在一个分层中矿石自然崩落首先 回采采用矿块式阶段自然崩落采矿法时,自然发生在应力最先超过强度处。在该处矿石因碎胀而堆崩落的矿石是近似水平的,采用其他阶段自然崩落采满下面的补偿空间,从而使上面的矿石不能再自然崩矿法时·发生自然崩落的矿石是呈倾斜状的(图1)。落。然后矿石自然崩落发生在分层的应力超过强度而 且下面有补偿空间的其他地…歹甸衬一{成 崩落完毕,便进行局部放矿。 图1阶段自然崩落采矿法局部放出的矿石体积,是整体 a一矿块式;b一盘区式;:一全面连续式矿石在自然崩落过程中碎胀 A一阶段走向;D一底柱;K一崩落矿石;Y一崩落岩石;的体积。经过局部放矿,待自 1、2、卜各开采单元得小的先开采然崩落矿石下面重新有了补 偿空间,下一个矿石分层才开始自然崩落。对于有倾斜椒…牛 4益,应通过模拟放矿确定从崩落矿岩接触面投影下的 图2矿块式阶段自然崩落采矿法各个放矿点放矿的顺序和每次放出的矿石数量,以及 1一矿体;2一围岩;3一阶段运输平巷;截止放矿时的放出矿岩品位。采用阶段自然崩落采矿 4一阶段运输横巷;5一人行通风天井;。一溜井;法时,由于大块矿石多,多使用铲运机出矿,其次是用 7一耙矿巷道;8一联络巷道;9一矿块切帮巷道‘电把或重力出矿。与用电耙或重力出矿相比,用铲运机 10一矿体自“弋匆鬃飞11一崩落矿石’出矿时,大块矿石堵塞放矿点喉部的频率到碍多。但 不宜将放矿点布置太密。 1 79评价与阶段强制崩落采矿法相比,阶段自然崩落采矿法的优点是开采成本低、劳动生产率高、开采强度大。其缺点是对使用条件的要求严格、对技术水平和管理水平的要求高。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条